Some of our projects
Warehouse move
Warehouse 600 sq. meters Height 11 to 14 meters
Our second project in 2025, a team of five professionals will carry out work in the Kuehne + Nagel warehouse (Bâtiment 3) in France fr.kuehne-nagel.com, dismantling and reusing part of the racking, while moving another section to a new location.
We started this work on February 3 and estimate that we need approximately three more days to complete the transfer of all the racking to the new warehouse.
Our team is committed to ensuring an efficient and smooth transition, ensuring that all operations are carried out with the utmost professionalism and in the shortest possible time.












Warehouse move
Each section measures 3 meters, The length of the conveyor is 50 meters, Conveyor length 297 cm
CTLOG International Saint-Martin-de-Crau, France
Dismantling - packaging - loading
3 employees working 3 days of work
January 27-28-29








The projects were completed before the formation of R, Dam MB


21 rue Ferdinand Buisson à Changé
from 18 july till 15 August/ 2024
Montage Palracks from Zero


Food products supplier
10 Rue Copernic, 53810 Changé, Francia
from 01.02 till 21.02 / 2024
Drive-in


32 Rue de l'Industrie, 60000 Beauvais, France ( ID logistics )
from 12.02 till 05.03
Palracks with thin metal


37 Rue de la Tresorerie 62126 Wimille
from 04.03 till 16.03
United Petfood France SAS
Drive-in


TIKAMOON, Port de Santes, 8 Ème Rue, 59211 Santes, Francia
Santes Tikamoon
from 18.03 till 23.03
Palracks